Permits by county
Well permits in Bay County
In Bay County there is no health department delegation in place, so a water well construction permit is issued by Northwest Florida Water Management District itself.
The authority
Northwest Florida Water Management District
Bay County has the simplest permitting answer on this whole site, and it is the opposite of the Jacksonville one. There is no health department delegation and no city agency in the way: the Northwest Florida Water Management District issues every well construction permit in the county itself. Verified 2026-09-17 against the Department of Health's own list of 22 delegated county health departments, on which no Panhandle county appears, and against the District's well permit guidance, which states that a Florida licensed water well contractor applies to the District before construction begins.
- Water management district
- Northwest Florida Water Management District
- District rule chapter
- Chapter 40A-3, Florida Administrative Code
- State construction rule
- Chapter 62-532, Florida Administrative Code
- Contractor licensing rule
- Chapter 62-531, Florida Administrative Code
The District issues it, for the whole county
In Bay County a water well construction permit is issued by the Northwest Florida Water Management District itself. There is no county health department delegation and no city agency holding one, so there is a single answer that does not change from one parcel to the next.
Two things establish that rather than one. No Panhandle county appears on the Florida Department of Health's published list of delegated county health departments; and the District's own well permit guidance tells a Florida licensed water well contractor to apply to the District before construction begins. The absence and the instruction agree.
A different chapter of the code
The Northwest Florida district's well rules are Chapter 40A-3 of the Florida Administrative Code. The districts covering the Jacksonville side of the state work under Chapters 40C-3 and 40B-3. Those are separate rulebooks administered by separate offices.
What does not change anywhere in Florida is the statewide construction standard in Chapter 62-532 and the contractor licensing requirement in Chapter 62-531. The licence is a state licence, not a regional one, which is why a contractor can work both ends of the state; the application route is what has to be learned separately.
The simplest permitting answer on this site
It is worth putting Bay County next to Duval to see how much the answer moves. In Duval the permit comes from the City of Jacksonville, whose Environmental Quality Division holds the St. Johns River district's only delegation agreement with a local government. In Bay County there is no delegation at all and the District does it.
Neither is harder than the other once you know which it is. Nearly all of the difficulty in Florida well permitting is not the process, it is finding out which of several offices the process runs through, and that is the part this page exists to answer.
Planning well work in Bay County
Ask before the schedule is fixed, not after.